PQR / WPS Test Checklist
PQR / WPS Test Checklist
What Job welding Inspector before, during and after PQR / WPS Test(procedure qualification test) ?
Below some checklist which can help you before PQR / WPS Test(procedure qualification test) start :
PQR / WPS Test Checklist
No | Item Description | Check, Review, Verify | |
Yes | No | ||
Before Procedure Qualification Test Start | |||
1 | Proposed WPS ready on test location or not ? | √ | |
2 | Welding Machine Calibration Record ? | √ | |
3 | Polarity as per proposed WPS ? | √ | |
4 | Tang Ampere, Volt Meter, Temperature Gauge, Welding Gauge available on test location ? | √ | |
5 | Material test Mill Certificate, Electrode available and accordance with proposed WPS ? | √ | |
6 | Positions of weld as per proposed WPS or not ? | √ | |
7 | Check 1G,2G,3G,4G,5G,6G or…..? | √ | |
8 | Joint Design accordance with proposed WPS ? | √ | |
9 | Check Angle, Root face, Root Gap, Thickness ? | √ | |
10 | Make Identification for test material(specimen) ? | √ | |
11 | Attended by all Party(clients,fabricator,3rd party, Government representative) ? | √ | |
During Procedure Qualification Test Start | |||
1 | Record Start time of test ? | √ | |
2 | Record Ampere, Voltage, Temperature ? | √ | |
3 | Inspect Root penetration as per code/standard or not ? | √ | |
4 | Attend, inspect, review during test and record all non conformance out of proposed WPS ? | √ | |
5 | Sign result and data of proposed WPS ? | √ | |
After Procedure Qualification Test Start | |||
1 | Review NDT result ? | √ | |
2 | Attending during Destructive Test ? | √ | |
3 | Review and Approve WPS as per Code/Standard ? | √ | |
4 | Copy and Keep(documentation/File) Approved WPS with WPS Registered | √ | |